How Much Does a Kitchen Remodel Cost in Columbus — and How Long Does It Take?

A clear, honest breakdown of 2026 price tiers, where the money goes, realistic timelines, and resale return — from the design-build team that builds these kitchens every week.

A recent Upper Arlington kitchen — fully custom Amish cabinetry, natural-stone backsplash, 36” Wolf dual fuel range and a vented statement hood.

 

A kitchen remodel in the Columbus area generally runs $20,000 to $350,000 in 2026, and takes 3 to 22 weeks of construction — depending almost entirely on one thing: how much you're changing.

That's a huge range, and we're not going to pretend otherwise. A countertop-and-backsplash refresh and a full down-to-the-studs reconfiguration with custom cabinetry are different projects with different price tags. The good news: once you know which kind of project you're actually after, the number gets a lot more predictable.

Columbus generally runs about 10–15% below the national median for kitchen work, thanks to Midwest labor and material costs. But the premium suburbs we work in — Upper Arlington, Grandview, Dublin, and Worthington — tend to land in the mid-to-high tiers, both because of the scale of the homes and because the investment aligns with long-term values in those zip codes. Below, we've broken kitchens into four clear tiers using real ranges from projects we actually complete.

 

THE FOUR TIERS

Kitchen remodel cost by project type

Use these to find roughly where you fit. Construction times are on-site build only — they don't include design, planning, or material lead times, which we cover further down.

Project Type Typical Investment (2026) Est. Construction*
Kitchen RefreshSame layout $20,000 – $50,000 3–5 weeks
New Kitchen, Same LayoutSame footprint $50,000 – $110,000 6–10 weeks
New Kitchen, New LayoutStructural changes $100,000 – $250,000 10–16 weeks
Designer / LuxuryHighest level $200,000 – $350,000 14–22 weeks

Kitchen Refresh — $20K to $50K

3–5 weeks · same layout

The fastest, most budget-friendly way to make a kitchen feel new without touching the layout. Typically includes new countertops, sink, faucet, and disposal; a new backsplash; new cabinet hardware plus either freshly painted existing cabinets or new semi-custom cabinets; paint on walls, ceiling and trim; and new decorative and task lighting. Best when the layout already works and the cabinet boxes are in good shape.

New Kitchen, Same Layout — $50K to $110K

6–10 weeks · same footprint

A full reset in the same footprint — everything comes out and goes back in new, but we're not moving walls, plumbing, or the major appliances. Typically includes fully custom, Amish-made cabinets and hardware; stone countertops (usually granite or quartz) and a tile backsplash; new sink, faucet and disposal; appliance installation; paint; and new lighting. Best for an aging or builder-grade kitchen ready for true custom cabinetry where the existing layout still serves you.

New Kitchen, New Layout — $100K to $250K

10–16 weeks · structural changes

Where a kitchen gets reimagined, not just refinished. Changes can include adjusting the layout (and often the surrounding rooms), adding or removing walls, relocating the sink, range, or appliances, changing window and door openings, adding square footage, or relocating the kitchen entirely. On top of the structural work it includes fully custom Amish cabinets, stone counters and backsplash, new sink/faucet/disposal/appliances, finish carpentry, layered lighting, paint, and new flooring. Best for a “forever home” where the current kitchen fights you every day.

New Kitchen, Designer / Luxury — $200K to $350K

14–22 weeks · highest level

Everything in a new-layout kitchen, executed at the highest level: fully custom Amish cabinets; natural stone counters (marble, Taj Mahal, quartzite); natural-stone or detailed-pattern backsplashes; a statement sink and real brass faucet; premium appliances (a 48"–60" range, oversized refrigeration, beverage fridges, double ovens, ice makers, a custom vented hood); layered lighting; new flooring; and features like a butler's pantry, wet bar, scullery, or messy kitchen.

Designer kitchens sit at the top of the 14–22 week range. A scullery, extensive trim and painting, cabinets that install on top of the countertops, and full-height stone backsplashes — which require two separate install visits — each add steps that extend the calendar.

 

THE BREAKDOWN

Where your money actually goes

Knowing the total is one thing; knowing where it goes is how you make smart trade-offs. Here's roughly how a mid-to-upper Columbus kitchen breaks down.

Cabinetry
35–45%
Labor & PM
20–30%
Appliances
10–20%
Countertops
10–15%
Floor · tile · light · paint
10–15%
Design · permits · contingency
5–10%

Cabinetry is the single biggest line item — higher for us than the 25–40% in generic guides, because our cabinets are fully custom and Amish-made rather than stock or semi-custom.

Countertop cost by material

Typical installed ranges in Central Ohio for 2026 — the choice homeowners ask about most.

Material Installed / sq ft Notes
Granite $50–$100 Classic, durable, huge variety
Quartz $60–$120 Most popular here — low maintenance, consistent
Quartzite $90–$200 Natural stone, marble look, harder than marble
Marble $100–$250 True luxury; requires sealing and care
 

LEVERS

What pushes your number up — and what brings it down

Two kitchens in the same neighborhood can price tens of thousands apart. We account for the “up” factors during your consultation, so they're built into your quote rather than sprung on you later.

What pushes it up:

  • Concealed conditions. Plaster walls, dated wiring, old plumbing and undersized panels are common in older UA, Grandview and Worthington homes — we scope for these so they're in your number from the start.

  • Scope of layout change. Moving a sink, opening a wall, or relocating the kitchen adds plumbing, electrical, and sometimes structural work.

  • Finish level. Quartz to natural stone, or a standard range to a 60" statement range, is where the top of each range comes from.

What brings it down — without cutting quality:

  • Keep your existing layout. If the sink, range, and refrigerator stay put, you skip the most expensive parts — plumbing moves, electrical reroutes, and structural work.

  • Mix "save" and "splurge." Design-build lets us put budget where it shows — one statement appliance or a stone island — and economize where it won't be missed.

  • Choose quartz over natural stone for the look of marble with none of the maintenance — and bundle projects to cut mobilization and permitting overhead.


None of the "up" factors are reasons to fear a remodel. They're reasons to plan one properly — which is what we do for a living.

 

THE SCHEDULE

How long does a kitchen remodel take?

The construction times above — 3 to 22 weeks — are the on-site build. The full project, from first meeting to the day you cook in it, is longer. That's true of every quality remodeler. Here's the honest version, in three phases.


Phase 1: Design & Planning — 2 to 4 weeks

Selections get made and the kitchen gets drawn. For fully custom cabinetry, we produce shop drawings — 2 to 4 weeks, including an on-site measure and one round of edits. Nothing gets built until those drawings are approved; that approval locks your design and greenlights the build.

Phase 2: Material Lead Times (the part people underestimate)

Once your design is approved, materials get ordered — and the good stuff takes time to make:

Material Lead Time
Fully custom Amish cabinetsFrom approved shop drawings 10–14 weeks
Semi-custom cabinets 4–8 weeks
CountertopsMeasured after cabinets are set ~2 weeks
Backsplash materials 3–6 weeks
AppliancesSpecial-order 2–14 weeks
Plumbing & light fixturesSpecial-order 2–10 weeks

Cabinet and appliance lead times are the biggest drivers of the overall calendar — which is why a kitchen is a months-long project even though "construction" is measured in weeks.


Phase 3: Construction (on-site)

How the on-site work typically sequences:

  • Permits (7–30 days): 2-5 days to prepare and file, then 7-30 days for approval. We prepare drawings of the existing and proposed layouts, a written scope of work, and anything else your local building department requires; approval time varies with the season and municipality.

  • Demo and Site Protection (1–2 days)

  • Engineering (1-5 days): If your project involves structural changes, an engineer reviews them and signs off on how they’re built to keep the structure safe - a required part of the framing process.

  • Framing (1–6 days): Only needed if your project requires adding or modifying framing

  • Rough Plumbing (1-2 days)

  • Rough Electric (1-3 days)

  • Rough HVAC (1-2 days)

  • Rough inspections: On permitted jobs, framing, insulation, plumbing, electric, HVAC and gas line (if applicable) all have to pass before drywall can start.

  • Drywall (~1 week): Includes everything from hanging to final sanding, including drying time between coats.

  • Cabinet install (2–4 days): Timing here depends on layout complexity

  • Countertops (~1 day): Note that these are measured after cabinets are installed

  • Backsplash (1–2 days)

  • Appliance Install (1–2 days)

  • Finish Plumbing (1-2 days)

  • Finish Electric (1-2 days)

  • Finish Carpentry (1-2 days)

  • Painting (3–6 days)

  • Final inspections: On permitted jobs, final sign-offs on plumbing, electric, gas line (if applicable) ), HVAC and final occupancy.

The takeaway: plan your project around the lead times, not the install days. If you want a finished kitchen by the holidays, the design conversation needs to start months ahead — and the homeowners who plan early get the calendar they want.


RETURN

Is a Kitchen Remodel Worth It in Columbus?

We believe in honesty over salesmanship, so here's the straight version. The 2025 Cost vs. Value Reportfound a minor kitchen remodel recoups roughly 113% of its cost nationally — the only interior project in the national top five for return. A major upscale kitchen remodel recoups around 36%.

That gap is the most useful number in this whole guide. A targeted refresh returns a higher percentage than a full gut renovation that costs five to ten times more. So the honest guidance:

  • Selling in 1–2 years? A refresh ($20K–$50K) is the smarter financial play.

  • Staying 5+ years? A full or designer remodel is a lifestyle investment that still recoups a meaningful share while you enjoy it every day.

One Columbus-specific guardrail: avoid over-improving for your block. A common guideline is to keep a kitchen within roughly 5–15% of your home's value. In UA or Dublin that supports a substantial budget; in a more modest neighborhood it's a reason to scope carefully. A good design-build partner will tell you the truth here.

 

Tariffs — and Why Domestic Cabinetry Matters

Tariffs on imported kitchen cabinets and vanities were set at 25% in late 2025, with further increases scheduled into 2026. Domestically manufactured cabinet lines are not subject to those increases.

Our cabinets are fully custom and Amish-made here in the U.S., which means your single largest line item is insulated from the import-tariff swings hitting projects built around overseas cabinetry. It's one of the quieter advantages of how we build — and a reason locking in pricing sooner rather than later can save money.

 

NO SURPRISES

How You Get an Exact Price — Not Just a Range

The four tiers above are planning ranges — they tell you which neighborhood you're in before you've made a single decision. But you don't choose a contractor off a range, and we don't ask you to.

We start with a free, on-site consultation, where we walk your space, talk through scope, and get clear on the finishes it'll take. From that, we create a 3D rendering of your proposed layout and give you an exact quote — not a range, not a ballpark, a real number tied to a real plan. The only time that number changes is if you decide to add scope or request an upgrade outside the original proposal.

We don't do the under-scope-now, change-order-later routine that wrecks other people's remodels. The price you approve is the price you pay — unless you choose to change it.

What catches homeowners off guard — and how we prevent it:

  • Asbestos or lead paint in pre-1980 homes. We flag the risk during scoping so testing and any remediation are planned, not discovered mid-demo.

  • Hidden water damage or rot behind sinks and dishwashers. We assess known problem areas before quoting.

  • Electrical panel upgrades. Many older Columbus homes have 100-amp panels that can't handle a modern kitchen; we check capacity up front.

  • Dumpsters, permits, delivery and temporary-kitchen logistics. These are in our scope, not asterisks added later.

Because we finalize scope and a 3D-rendered plan before construction, these live in your fixed quote. If something truly unforeseeable appears behind a wall, you'll hear about it immediately — not at the end with a surprise balance.

IN THE WILD

Real Columbus Kitchen Projects

Ranges in a table are useful. Seeing what they actually buy is better. Here are recent kitchens we designed and built across Central Ohio.

Kitchen Refresh — Dublin · $20K–$50K

New quartz countertops, backsplash, island cabinetry, custom hood, and lighting in the existing footprint.

New Kitchen, Same Layout — Upper Arlington · $50K–$110K

Full custom-cabinet reset with quartz countertops, statement lighting, farmhouse sink, brass hardware and addition of a coffee station with custom shelving.

New Kitchen, New Layout — Upper Arlington · $100K–$250K

Opened up the entire 1st floor living space by removing 2 walls, including one load bearing, and installed a beam. Relocated the kitchen location to the center of the first floor and added in a mudroom off of the garage with custom locker storage.

A WORD ON BIDS

Why the Cheapest Quote Usually Costs the Most

The lowest bid wins on paper and loses in reality. A low number usually means the job was under-scoped to win it, or the gap gets made up in change orders once you're committed. Either way, the "savings" disappear by week three.

We work differently. Every Elevate project starts with real design and planning — full measurements, selections, and a 3D rendering of your new layout — so you're deciding from a complete picture before construction begins. You're hiring a fully managed build with vetted trade partners, not a crew juggling six other jobs. You're investing in a kitchen that's right the first time.

Other Columbus Remodeling Costs

Planning more than the kitchen? Bundling projects with one design-build team lowers mobilization, permit, and management costs.

Frequently Asked Questions

Ready to See Your Number?

We'll walk your space, talk through what you want, and follow up with a 3D rendering and an exact quote. No obligation.

Next
Next

Dublin, Ohio Primary Bath Remodel